Active jobs
7
5 on schedule, 2 behind
Read from the job files, the books and the field logs before anyone got in.
Active jobs
7
5 on schedule, 2 behind
Billed in September
$1.21M
105% of the $1.15M goal
Open invoices
$684K
$96K past 60 days
Gross profit, all jobs
23.1%
Target 22%, dashed
Waiting on a person
4
Ready to signReview
Next: Building C turnover on October 9. Pay application 9 is drafted and waiting on you.
Why it slipped: ceiling grid arrived 6 days late. Change order 14 for the added ceiling work is waiting on you.
Why profit dropped: bid at 22 percent. Corridor labor is running 11 percent over the estimate for three weeks.
Next: punch walk with the district on October 7. One invoice is at 64 days, and a reminder is drafted.
Next: floor 5 framing inspection on October 8.
Next: storefront glass lands October 6. A Saturday drywall shift would win back both days.
Next: final walk and closeout package on October 16. Retainage of $19K follows.
Drafted overnight. Nothing goes out until a person approves it.
Built from the schedule of values and Friday's field walk. Building C lines are held at 80 percent until the punch walk.
Priced from the unit rates in the original estimate. The owner's rep asked for it in writing on Thursday.
The district paid the last two invoices at 41 and 45 days. This one is the outlier, so the tone stays friendly.
Corridor labor has run 11 percent over the estimate for three weeks while the work itself is on schedule.
All four are signed off. The next build runs tomorrow at 6:00 AM.