Pulled overnight from the books, the job files, the field logs and every email. Read it in two minutes, sign off below, and the office takes it from there.
Signed off this morning
0 of 3 done
Cash in the bank
$842K
Collected Friday
$61.2K
Two checks, Linden Row and Alder Bay. Both posted.
Payroll Thursday
$148K
Covered with $694K left after.
Billed in September
$1.21M
105% of the $1.15M goal
Open invoices
$684K
$96K is past 60 days
Ranked by what waiting would cost. Nothing moves until you say so.
Profit slipped to 17.2 percent against a 22 percent bid. The suggestion: move two painters to Kestrel Park and finish the corridors with the smaller crew.
Drafted from the schedule of values and matched line by line to Friday's field walk. Building C is held at 80 percent until the punch walk.
The owner's rep wants a plan to win back the week. The reply is drafted with two Saturday shifts and a revised close-in date.
Drywall finish is trailing the plan. Storefront glass lands Tuesday, so the gap closes if drywall catches up this week.
The district usually pays in about 43 days. A friendly reminder is drafted in the billing queue.
418 hours against 380 budgeted last week, mostly on Wren Street and Cedar Hall. Both are catching up on schedule.